Manifold valve in the last when terminal ship line up is complete & verified, only then the terminal will open their tank valve. drop & ships tank valve is opened first when setting up lines. Please correct your answer
Marine MCQs4 November 2023 at 14:19GMT+5:30
Thanks for the comment... I apologize for not understanding your comment.... The correct sequence for opening the valves during loading by gravity is as follows:
1. Open the shore tank valve. 2. Open the ship's manifold valve. 3. Open the ship's drop line valve. 4. Open the valve for the cargo tank to be loaded into.
The answer is indeed C, "For the cargo tank to be loaded into." Opening this valve last ensures the controlled and directed flow of cargo into the specific cargo tank, minimizing the risk of spillage and ensuring a safe loading process. If you have any difference in opinion please comment....
2 comments
1. Open the shore tank valve.
2. Open the ship's manifold valve.
3. Open the ship's drop line valve.
4. Open the valve for the cargo tank to be loaded into.
The answer is indeed C, "For the cargo tank to be loaded into." Opening this valve last ensures the controlled and directed flow of cargo into the specific cargo tank, minimizing the risk of spillage and ensuring a safe loading process. If you have any difference in opinion please comment....